▸ Screw the lock pieces from the lock set to the base plate with the screws.
▸ Position the hood from the top.
▸ Insert the side holding catches into the counterpieces, twist and lock in.
▸ Fit the locking bracket on the base plate of the purge air unit.
▸ Attach the weatherproof cover and fix into place.
Fig. 66: Assembling the weatherproof cover for a purge air unit
7.6.6 Evaluation unit start-up
The evaluation unit is configured with a standard parameter set at the factory and,
therefore, is ready to start measurement operation immediately. With the exception of the
following steps, therefore, no additional measures are required for start-up for standard
applications:
▸ Based on the operator information in
“Handling the Evaluation Unit”, page 41, check
whether the measured values are output correctly on the LCD.
If error or warning messages are displayed:
▸ Use the operator information in “Handling the Evaluation Unit“ as well as the display
of error and warning messages in “Troubleshooting and Clearing Malfunctions”, page
104
to locate and rectify the error cause.
If the cause of the fault cannot be rectified with this information, contact the SICK AG
Service Dept. or the responsible sales partner for further coordination
▸ If necessary, parameterize the evaluation unit in accordance with the requirements of
the measuring task and the installation environment. See
“Handling the Evaluation
Unit”, page 41
.