116 / 244   
Siemens  Standard application AHU  CE1P3977en_02 
Building Technologies  Detail pages: Time switch program  01.02.2010 
–  Main Index > Unit > Main overview > Time switch program > Calendar 
exception 
–  Main Index > Unit > Main overview > Time switch program > Calendar fix 
off 
–  Main Index > Unit > Auxiliary > TSP Output > Calendar exception 
 
Parameter  Range  Function 
Present value   
−  Passive 
−  Active 
Displays whether a calendar entry is currently 
enabled: 
−  No calendar entry is currently enabled. 
−  A calendar entry is currently enabled. 
Choice-x   
−  Date 
−  Range 
−  WeekDay 
−  Passive 
Specifies the entry for the exception:  
−  A certain day (e.g. Friday). 
−  A period (e.g. vacation). 
−  A certain day of the week. 
−  Entries are ignored. 
This value should be set last after the date is 
entered. 
-(Start)date    −  Choice-x = range: Enter start date for the pe-
riod. 
−  (Choice-x = date: Enter data for a single day). 
-End date    Choice-x = range: Enter end date for the period. 
End date must always be after the start date. 
-Week day    For Choice-x = weekday only: Enter the day of 
the week. 
 
Only the entry in (start) is relevant. 
–  -(start) date = *,01.01.09 
Result: January 1, 2009 is an exception date.  
–  -(Start) date = Mo,*.*.00 
Every Monday is an exception day.  
–  -(Start) date = *,*.Evn.00 
The days for the entire month are exception day for each even month (February, 
April, June, August, etc.).  
 
The entries in (start) date and end date are relevant. 
–  -(start) date = *,23.06.09  /  -end date = *,12.07.09. 
June 23, 2009 through July 12, 2009 are exception days (e.g. vacation). 
–  -(start) date = *,23.12.00  /  -end date = *,31.12.00. 
December 23 through 31 are exceptions for each year. The entry end date = 
*,01.01.00 does not work here, since January 1 is before December 23. 
–  -(start) date = *,23.12.09  /  -end date = *,01.01.10. 
23. December 23, 2009 through January 1, 2010 are exception days. 
–  -(Start) date = *,*.*.00  /  -End date = *,*.*.00 
Caution! This entry is always enabled! The plant is continuously on exception or 
off. 
 
The entries for week day are relevant. 
–  Week day = *,Fr,* 
Every Friday is an exception day. 
–  Week day = *,Fr,Evn 
Each Friday in even months (February, April, June, August, etc.) is an exception 
day. 
–  Week day =  *,*,* 
Parameter 
Examples for 
Choice-x = Date. 
Examples for 
Choice-1 = Range. 
Examples for 
Choice-1 = WeekDay.  
Basis Document Siemens Climatix Control System
BDCX.100820.01GB
Page 116