Commissioning
4.7 Loading the project to the target device
Commissioning with Startdrive
136 Commissioning Manual, (IH3), 07/2016, 6SL3097-4AA10-0BP0
Loading the project to the target device
This function loads the actual project from the PG/PC into the Control Unit. A consistency
check is first made for the project. If inconsistencies are detected, then the corresponding
messages are output. You must resolve the inconsistencies before loading. If the data is
consistent, then it will be transferred into the work memory of the Control Unit. In order to
execute this function in the online mode, the following operator actions are alternatively
available:
1. Select the drive device and call the menu "Online> Load to device".
Or
2. Click on the icon
(Load to device) in the toolbar.