Figure 27: Position of the support feet
Requirements:
☐ The requirements for the foundation must be complied with (see "Information on Transport and Mounting of the
MVPowerStation").
☐ The pea gravel ground and the mounting option must be prepared (see "Information on Transport and Mounting
of the MVPowerStation").
☐ The support feet must be attached to the MVPowerStation (see Section4.6, page43).
☐ The length of the support feet on the MVPowerStation must be at least 350mm.
Risk of injury due to inappropriate transport of the oil tray
The oil tray for the MVPowerStation is very heavy. If you try to move the oil tray without auxiliary equipment, you
may suffer injury.
• Only transport the oil tray using a suitable means of transport.
• Using a suitable means of transport, transport the oil tray as close to the ground as possible.
Risk of injury if heavy service platforms are lowered too fast
The service platforms of the MVPowerStation are very heavy. If service platforms are folded down too fast or
dropped, persons could be injured.
• Have at least two people pull each service platform forwards and down.
• Always wear suitable protective equipment.
Damage to oil tray due to water undermining
In case of strong rain, the oil tray can be undermined and float away.
• Secure the oil tray against floating away.
Position of the cables when mounting the MVPowerStation
To prevent damage to the previously laid cables during mounting of the MVPowerStation, the cables must be
laid on the foundation as flat as possible.
4 Transport and Mounting
SMA Solar Technology AG
System ManualMVPS22JP-SH-en-1146