20. Install the rotary seal O-ring on each shaft.
21. Figure 127 shows the rotary seal O-ring installed on the
shaft.
22. Install the flush-side rotary seal onto the shaft, aligning the
tab with the notch on the seal.
23. Figure 129 shows the seal installed.
Figure 126 - Install O-ring
Figure 127 - O-ring installed
Figure 128 - Install flush-side rotary
seal
Figure 129 - Rotary seal installed