5 - 2 Te-Stack Operating Manual, 391862, en, V2.3
5 - Putting into Operation
Reinstalling the Te-Stack
5.2 Reinstalling the Te-Stack
After the initial installation by the Tecan FSE, the complete Te-Stack may be taken
off as a whole unit and may be replaced later. This task may be performed by the
operator, but only if
the configuration is not changed;
the customer has attended a special training for reinstalling.
5.2.1 Preparation
WARNING
Chemical, biological and radioactive hazards due to damaged plates or DiTis.
Danger of contamination.
Make sure that the instrument is decontaminated according to good laboratory
practice.
1 Switch the instrument off.
2 Pull the power plug to disconnect the instrument from the power supply.
3 Check if the instrument is leveled correctly.
Refer to the corresponding manual to level the instrument.
Note: Consult the Tecan FSE, if necessary.