Transportation and erection
Delivery of the machine
Conveyors up to a length of approx. 3 m are completely assembled at the
factory and are delivered with preadjustments. Longer conveyors are usually
delivered in part elements. The individual parts are marked with labels on the
section points. Supports, suspensions and other attachments are packed
separately and included in the delivery.
Unpacking the machine
Complete the following steps:
1. Move off all transport packaging
2. Check for possible transport damage.
3. Check that all items listed on the delivery note have been delivered.
Machine has been unpacked and is complete.
A longer storage period of the machine
At a storage time of more than 4 weeks, the conveyor belt must be deten-
sioned in order to prevent damages caused by bulges The procedure for
slackening off the belt is described under Repairs. If the machine is trans-
ported by sea, seaworthy packaging is required.
Observe the permissible operating conditions described in the following also
for storage periods.
For questions concerning storage and transport, please contact TRANS-
NORM SYSTEM GmbH.