Vertiv | SmartCabinet | User Manual 54
System Commissioning
3.2. Inspection
The following table (Table 3-1) describes the Pre-commissioning checks to be carried out:
Table 3-1
Inspection Items Inspection Criteria Remark
Distribution
Check, measure, and conrm if the AC mains voltage and frequency are
normal, and verify if the AC mains correction is correct without any short
circuit
Check and conrm if the distribution cables of UPS and PMU are correct
without any short circuit
Check if the installation and wiring of the congured battery is correct and
if the battery polarities, both negative and positive are correct.
Monitoring unit
Check if all the communication cables are connected in correct sequence
based on the wiring diagram and cable number
Thermal Management
system
Check if the air conditioner is charged with refrigerants
Check if the air conditioner pipes are connected correctly without leakage
Check if the emergency fan supply port is proper
Intelligent Lock
Check if the distribution and signal cables of the intelligent lock are
correctly connected based on the wiring diagram and cable number
For
specic
models
only
Check and conrm if the access control card can open the intelligent lock
in the usual way
Check the re ghting Check and conrm the re protection system node is normal access Optional
System
Check if the vacant space has been sealed by dummy plates
Check the isolated sheet metal parts in the sealed frame of the air
conditioner to ensure that the refrigerant pipe and the power supply
communication cables are led out from the top of the isolated sheet metal
part
• Before starting the Smart Cabinet, ensure that the maintenance bypass MCB of the MSC-PMU is
opened and locked by the sheet metal lock.
• Before startup, conrm that the SPD module color is green.
3.3. Startup and Commissioning
Prior to Startup of the SmartCabinet system, dial the service phone number (“400”) to authorize the
startup of the UPS. The following owchart (Refer Figure 3-2) depicts the startup steps to be taken while
commissioning.