Vertiv | SmartCabinet | User Manual 56
System Commissioning
6. Press the ON button on the UPS panel for 2s following which the inverter indicator (green) ashes, the
inverter starts up, and the inverter indicator turns on.
7. Measure and conrm if the inverter output voltage is normal. If the battery is not connected, the fault
indicator ashes; If the battery is connected, the fault indicator is o.
8. Close the air conditioner MCB and wait for the air conditioner to start up.
9. Close the PDU MCB and conrm if the displayed data of the PDU panel is normal, and check if the
indicators of the ports turn on one by one.
10. Close the LCD & LED MCB, open the front door and wait for the LED to turn on; after the LCD
communication becomes normal, log in to the SmartCabinet system and conrm that the parameter
display is normal.
11. If an intelligent lock is selected, close the intelligent lock MCB. The cabinet door should be closed only
after conrming that the access control card can open the lock.
For the cautionary measures in the UPS startup, refer to Liebert ITA 5kVA UPS user manual.
The PMU contains an SPD module; therefore, ensure that the PMU SPD MCB is closed when the
SmartCabinet is powered on for operation.
Before starting, ensure that the maintenance bypass switch is opened and is locked by a sheet metal
lock.
If an intelligent lock is selected, before opening it, conrm if the congured access control card can
open the intelligent lock
The startup of the SmartCabinet system should be completed by authorized professionals. Vertiv rec-
ommends an authorized personnel to carry out the Commissioning process.
Remember that the startup or commissioning has to be done correctly and therefore Vertiv recom-
mends its own subject matter experts and professionals for that task. In case of any discrepancy
caused due to incorrect startup from the user end (meaning the commissioning is done by the cus-
tomer at his site), the warranty will be void. Follow all the steps mentioned closely and implement it in
an accurate manner to rule out possible human errors while commissioning/startup.
3.4. System Commissioning
Following are the steps to be observed for System Commissioning:
1. On startup, the following screen as shown in Figure 3-4 is displayed on the LCD screen: