3.4.4 Inspection of air hoses (Foundry Prime)
General
The air hoses on Foundry Prime robots must be inspected for leakage every six
months.
Required equipment
Art. no.Equipment, etc.
-Leak detection spray
-Pressure gauge
-Cut off valve
Procedure
For this test it is recommended that the air supply to the robot has a pressure
gauge and a cut-off valve connected.
NoteAction
Recommended pressure:Apply compressed air to the air connector on
robot base, and raise the pressure with the
knob until the correct value is shown on the
pressure gauge.
1
0.2-0.3 bar
A
B
C
xx0600003341
A: Air Connection
B: Pressure gauge
C: Cut off valve
It should take at least 5 seconds for the
pressure to reach 0 bar.
Close the cut off valve.2
The time is < 5 seconds:
If the answer is YES: Localize the
leakage by following the procedures
below.
If the answer is NO: The system is OK.
Remove the leak testing equipment.
3
Pressurize by opening the cut off valve.4
Spray suspected leak areas with leak detec-
tion spray.
Note
Bubbles indicate a leak.
5
Continues on next page
106 Product manual - IRB 4400
3HAC022032-001 Revision: Q
© Copyright 2004-2018 ABB. All rights reserved.
3 Maintenance
3.4.4 Inspection of air hoses (Foundry Prime)