9 Maintaining the PTV Inlet
To Install a Capillary Column with the Programmable Temperature Vaporization Inlet
Maintaining Your GC 149
Figure 33. Insert Smart ID key
13 Configure the new column.
14 Condition the column per the manufacturer’s recommendation. See To Condition a
Capillary Column.
15 Install the column into the detector.
• To Install a Capillary Column in the FID
• To Install a Capillary Column in the NPD
• To Install a Capillary Column in the TCD
• To Install a Capillary Column in the ECD
• To Install a Capillary Column to the FPD+
16 Exit maintenance mode. Select Maintenance > Instrument > Perform Maintenance >
Maintenance Mode > Finished.
17 After the column is installed at both inlet and detector, establish a flow of carrier gas and
purge as recommended by the column manufacturer.
18 Restore the analytical method.
• For FPD+, immediately turn off the flame.
• For NPD, immediately turn off the bead.
19 After the GC becomes ready, wait 10 minutes then ignite the detector flame or adjust
offset on the NPD bead.
Be careful! The oven, inlet, and/or detector may be hot enough to cause burns. If they are hot,
wear heat-resistant gloves to protect your hands.
20 Allow the oven, inlet, and detector to equilibrate at operating temperature, then retighten
the fittings.
21 Perform an inlet Leak & Restriction test and reset the maintenance counters.