3.1 - Installing the HRC
70
3 - INSTALLATION
3.1.1 - Installation site
The Heat Pump must always be transported in a vertical position,
even during installation. It should be transported using a
forklift truck. Do not use the hydraulic connections to move the
appliance, take hold of it using the four bottom corners.
The installation must be carried out by a quali ed installer, taking
all necessary precautions to avoid any risk of accident or any
material damage.
The Heat Pump is speci cally designed to be installed outdoors,
in an open space which is not subject to excessive dust. Under no
circumstances must it be installed in enclosed premises.
It is designed to operate in rain, but it can also be installed under
a shelter as long as it is well ventilated (the opening should be
large enough to ensure that air can  ow freely to the air intake
point and rejection points on the fan).
Noise levels coming from the installation
ON THE GROUND OR
ON A PATIO
(open space)
NEXT TO A WALL
+ 3dB (A)
IN A CORNER
+ 6dB (A)
IN A YARD
+ 9dB (A)
TO THE SIDE OF A WINDOWUNDER A WINDOW
THE NOISE SCREEN MUST BE MADE FROM
INSULATED MATERIALS
CORRECT
CORRECT