Suitability and functionality of technical ventilation systems, gas warning systems, inerting devices,
devices, protective systems, or control or regulating devices in the sense of Directive 2014/34/EU as
well as explosive devices in the sense of TRGS 725
Suitability and implementation of the measures determined on the basis of the risk assessment
Suitability, functionality, and installation of work equipment and related connection devices that are not
devices, protective systems, or safety, control, or regulating devices in the sense of Directive
2014/34/EU, but are relevant for explosion protection
Suitability of other work equipment, such as ladders, containers, tools, for use in hazardous areas
Suitability and functionality of other equipment and building components related to explosion protec-
tion (e.g. lightning protection systems, conductivity of floors and linings)
Suitability of the personal protective equipment(PPE (e.g., the electrostatic discharge capacity of work
shoes or gloves )
The existence and legibility of the labels for potentially explosive areas in which measures to avoid
ignition sources are required
The existence and suitability of the organizational measures required for explosion protection
The implementation of measures relevant to explosion protection from official requirements
Certificates proving the correct installation of system parts, provided that their correct installation can-
not or only partially be ascertained during the technical inspection, e.g. flame-arresting fittings or limit
switches
7.4.1.3 Checking the deadlines for the recurring tests
When doing so, assess whether the system can be operated safely until the next specified recurring test.
7.4.1.4 Verifying the maintenance plan
When doing so, assess whether the maintenance plan is suitable for maintaining the safety of the Ex
system until the next recurring test. The maintenance plan can also be used to test the technical protecti-
ve measures for explosion protection of the explosive system. It can also be part of an integrated ma-
nagement system.
Definition of responsibilities for the maintenance plan, definition of maintenance and inspection
content, e.g. when creating work plans, processing the maintenance and inspection content, e.g. in
the form of work plans, the assessment of deviations from the target state, and any necessary repairs.
Determination of maintenance and inspection measures and deadlines for devices, protective sys-
tems, safety, control and regulating devices as well as their connections and interactions, technical
ventilation systems, gas warning devices and inerting devices and MSR devices for explosion protec-
tion
Comprehensible description of the required maintenance measures and deadlines e.g. in the form of
work plans, work equipment of comparable design can be summarized.
Implementation of the maintenance plan: Implementation of maintenance and inspection in ac-
cordance with the defined maintenance plan, notification of completion of the implementation of main-
tenance and inspection, documentation of identified repair needs and implementation of the repairs.
Necessary maintenance measures must be carried out immediately. Maintenance work must be car-
ried out by qualified specialist personnel who have sufficient experience in the maintenance of Ex sys-
tems based on the maintenance plan. The maintenance plan and the implementation of maintenance
measures must be clearly documented.