3.3 Unpack and inspect
WARNING
You must use suitable lifting equipment to move the iH system. It is too
heavy to lift by hand.
WARNING
Ensure that the maximum angle between paired slings used to lift the iH
system is 45
o
.
The iH system is supplied sealed in a foil bag. To prevent contamination of the iH system,
before you unpack and inspect the iH system we recommend that you move the pallet as
close as possible to the clean area in which you will install the system. Remove the foil bag
carefully; use the bag as a dust cover while you wheel the iH system to its final operating
position.