EasyManua.ls Logo

Bruker CryoProbe System - System Relocation and Disposal; Relocation, Storage, and Disposal Procedures

Bruker CryoProbe System
93 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
CryoProbe Installation BRUKER 69 (93)
Relocation of a
CryoPlatform 6
6000000
Relocation 6.1
0
This section applies to moving a CryoProbe System to either a storage room or to
another NMR spectrometer. If storage in a pressureless state is required (not rec-
ommended!), see "Pressure release" on page 70
.
For disassembling the CryoProbe System, use the reverse order of the installation
sequence "Initial setup" on page 17
. Consider also the CryoProbe Site Planning
Guide.
Before moving the CryoProbe System to a different magnet, make sure that the
new magnet qualifies (clearance between shim system and floor, blue spinner tur-
bine stator etc.)..
CryoProbe System storage 6.2
0
The CryoProbe System must be stored in a clean, dry, and non-corrosive atmos-
phere. Minimum requirements are: -20° to + 50°C, humidity max. 95% (non con-
densing).
Put the Protection Cap on the CryoProbe sample cavity and make sure that the
Vacuum Plug is in place at the bottom. Close the CryoCouplers on CryoProbe and
He Transferline tightly with their special protective caps. Wrap the whole
CryoProbe (or at least its tube) in airtight plastic film and stow it in its case. There
is no preferred storage orientation for the CryoProbe case.
Use individual airtight plastic bags for all small parts like Tuning Adapter, Vacuum
Adapter etc.
CAUTION: Any contamination can have severe effects on shimming, background
signal, vacuum insulation etc.
Disposal 6.3
0
Disassembly and disposal of a CryoPlatform should be carried out by technically
trained personnel only.

Table of Contents

Related product manuals