PB 1.1-2007
Page 15
Section 8
INSTALLATION OF CABINET FRONT
8.1 CABINET FRONT OR TRIM PACKAGE
The cabinet front or trim package is designed to prevent damage to the front during shipment and handling.
8.2 UNPACKING
Care should be used when unpacking and handling the cabinet front.
8.3 COVERS AND DOORS
Install covers, close doors, and make certain that no conductors are pinched and that all enclosure parts are
properly aligned and tightened.
8.4 TOUCH-UP
A suitable paint or other corrosion-resistant finish should be applied to those places where the finish is
damaged.
8.5 FRONT ALIGNMENT
The cabinet front may be provided with an adjusting means to align it squarely with the building even though
the cabinet may be slightly out of plumb with the building.
© Copyright 2007 by the National Electrical Manufacturers Association.