EPSON Stylus Pro 9000 Revision B
Disassembly & Assembly Disassembly Flow 88
REMOVING THE CR MOTOR/PULLEY ASSEMBLY
1. Remove the L/R Side Covers as described in L/R Side Covers Removal”
on page 75.
2. Manually release the Carriage Lock and move the carriage away from the
capping position.
3. On the Left Side Frame, find the CR Driven Pulley and loosen the two
screws securing it to the frame. Then loosen the tension on the steel belt.
Figure 4-23. CR Motor Removal & CR Steel Belt Loosening
4. Towards the right side of the frame there is one screw securing the steel
belt, remove this screw. Then remove one edge of the steel belt, and finally
pull out the steel belt to the Right Side Frame.
Figure 4-24. CR Motor Removal/Steel Belt Removal
5. Loosen the Hex (Allen key) screw (2.5mm), and then remove the bearing
stopper attached to end of the CR Motor Shaft.
ADJUSTMENT
REQUIRED
When removing the CR Motor, the following adjustment
procedures are required.
n CR Steel Belt Tension Adjustment