Preventive Maintenance
Fox Maintenance © Essemtec AG 4-11
0000074/05
/ March 31, 2017
Pusher needles
To prevent nozzle damages, use genuine
Essemtec pusher needles (SP26/BN01).
Time needed
Schedule around 31 minutes for this task (preparation time of 3 minutes included).
Do not forget to include the time consuption for the daily maintenance which is due at the same
time.
4.4.2 Prerequisites
For a safe and efficient maintenance, detailed in this chapter, the following prerequisites have to
be fulfilled:
• Production Material unloaded
• Feeders on front side removed
• Nozzles, does not matter
Machine operating condition:
• in operation
• machine at maintenance position
Schedule around 3 minutes to fulfill these prerequisites (see also chapter 'Tools, Material and
Scheduling' for the overall effort).
To gain the above mentioned prerequisites, follow the steps described in chapter "Gaining
Prerequisites a" on page 4-62.