Preventive Maintenance
4-26 © Essemtec AG Fox Maintenance
0000074/05
/ March 31, 2017
Time needed
Schedule max. 17 minutes (without dispense axes) / max. 27 minutes (with 2 dispense axes) for this
task (preparation time of 3 minutes included).
Do not forget to include the time consumption for the daily and weekly maintenance which are
due at the same time.
4.6.2 Prerequisites
For a safe and efficient maintenance, detailed in this chapter, the following prerequisites have to
be fulfilled:
• Production Material unloaded
• Feeders on front side removed
• Nozzles, does not matter
Machine operating condition:
• in operation
• machine at maintenance position
Schedule around 3 minutes to fulfill these prerequisites (see also chapter 'Tools, Material and
Scheduling' for the overall effort).
To gain the above mentioned prerequisites, follow the steps described in chapter "Gaining
Prerequisites a" on page 4-62.