EasyManua.ls Logo

GE FVP110 - Piping

GE FVP110
292 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
FVP 110 Fieldbus Valve Positioner Manual
36
GE Energy
Installing FVP110 on a Linear-motion Control Valve
This section gives the general installation procedure when assembling an FVP110 with a
linear-motion control valve (e.g., a globe valve) combined with a diaphragm actuator or
cylinder actuator (Figure 15). The most suitable procedure may differ depending on the
shapes of the bracket and valve actuator, and the structure of the mounting position.
Figure 15 FVP Installed on Linear-motion Valve/Actuator
1. Attach the bracket to FVP110 using the four M8 bolts supplied (See “Part Names” on
page 33).
2. Choose the appropriate feed back lever. The FVP110 with option code /LV1 comes
with two different feedback levers, (1) and (2), and the one with option code /LV2
comes with lever (3) (Figure 16). Check the specifications of the levers (Table 1) and
choose the lever most suitable lever by valve.
Figure 16 Feedback Levers

Table of Contents

Related product manuals