Chapter 8 - Replacement Procedures 8-89
D
IRECTION 5771498-100, REVISION 6 VENUE™ SERVICE MANUAL
PRELIMINARY
13.)Remove the articulated arm.
Note: Ensure the pressure pin is not dropped (if exists)
8-6-4-5 Arm Installation Procedure
1.) Install the new arm on the riser.
2.) Install the Teflon ring and then the C-clip.
3.) Route the cockpit (monitor) cables through the riser opening, refer to MPB TO Cockpit Cable
Installation Procedure and BE to Cockpit Cable Installation Procedure
4.) Route each cockpit (monitor) cable through the arm side and install the arm side covers.
5.) Re-connect the ground cable to the riser
6.) Secure each side cover with two securing screws.
7.) Install the arm base cover.
8.) Install the following covers: Lower Front eTower cover, Left Side eTower cover, Right Side eTower
cover, Riser Thermal Cover and RS Probe Cover.
Figure 8-73 Removing Scanner Arm
Figure 8-74 Pressure Pin