• Repeat this operation three times and then, after the final rinse, open the lid and check that the hopper is empty. If it
is not, close the lid and press the TurboFiller suction valve until it is completely empty.
IMPORTANT! Carefully clean the TurboFiller once the treatment is complete to ensure that it is clean before treating
other crops which could be sensitive to the products that have just been used. For more information, see section
Cleaning page 49"Cleaning".
Agitation prior to resuming treatment
If treatment has to be interrupted for a time, major or minor
sedimentation can occur. Before resuming treatment, the mix must be
homogenised.
1. Turn the suction valve (1) to "main tank". Turn the discharge valve
to "Spray" and the agitation valve to "Agitation". Close the other
valves.
2. Turn the suction valve (1) to "main tank". Turn valve (2) to
"Agitation" and the pressure valve (3) to "Spray". Close the other
valves.
3. Switch on the pump and set the power take-off to 540 rpm.
4. Allow agitation to continue for at least 10 minutes, or longer
depending on the mix.