Step 7 After the electric heater commissioning, the humidifier commissioning screen is displayed.
Verify that the main water inlet valve is open. Check whether the humidifier pipes and the
solenoid valve leak.
If yes, select Leak, and tap Submit. The commissioning has failed. Locate and repair the
leak points.
If no, select No leak, and tap Submit within the time limit displayed on the screen.