NetCol5000-A 42 kW Air Cooled In-row Precision Air
Conditioner
User Manual
4 Commissioning
Issue 01 (2017-07-27)
123
Figure 4-37 Humidifier commissioning
Step 8 After the humidifier commissioning, the condensate pump commissioning screen is displayed.
Check whether the condensate pump vibrates and generates operating sound.
If yes, select Yes, and tap Submit within the time limit displayed on the screen.
If no, select No, and tap Submit. The commissioning has failed. Locate and rectify the
faults of the condensate pump.
Figure 4-38 Condensate pump commissioning
Step 9 After the condensate pump commissioning, the cooling system commissioning screen is
displayed. Check whether the electric heating belt is firmly attached to the compressor outer
wall and whether there is noticeable temperature rise by touching the belt surface.
If yes, select Yes, and tap Submit within the time limit displayed on the screen.
If no, select No, and tap Submit. The commissioning has failed. Locate and repair the
faults of the electric heating belt.