a) If you are already connected to the ASMI, go to the next step. Otherwise, click All Systems then
select system being serviced. Then, click Actions > View All Actions > Launch Advanced
Systems Management (ASM).
b) In the navigation area, expand System Service Aids > Cable Plugging Validation. Then, click
Validate UPIC Cables. The system veriîš³es that the UPIC cables are present.
Note: Older îš³rmware levels do not support validating the UPIC cables while the system is at FSP
standby. You can skip this step if it is not available.
c) Expand System Service Aids > Cable Plugging Validation. In the Display Cable Status section,
select UPIC Cables and click Continue. The system validates that the UPIC cables are installed in
the correct locations and displays a table with the results. Ensure that the plugging status is OK for
each cable in the displayed table. If the status is OK, no further action is required. If the status is
not OK, review the error logs, correct the problems, and repeat steps b and c as needed until the
status is OK for all cables.
d) Exit the ASMI and continue to the next step.
6. If you powered off the system, from the Operation list, select FRU Level Activate. Then, click OK to
conîš³rm the operation.
7. From the Operation list, select Reset Identify LED. Then, click OK to conîš³rm the operation.
UPIC cables
Preparing the 9080-M9S system to remove and replace a UPIC cable
To prepare the system to remove and replace a UPIC cable, complete the steps in this procedure.
Procedure
1. From the Operation list, select Set Identify LED. Then, click OK to conîš³rm the operation.
This action causes the identify LED for the faulty part to turn on, and causes the blue system ID LED to
turn on.
2. Use the blue LED to identify the server.
Ensure that the serial number of the system matches the serial number to be serviced.
3. If you powered off the system, from the Operation list, select FRU Level Deactivate. Then, click OK to
conîš³rm the operation.
4. Check that an amber identify LED (A) is flashing for one of the UPIC cables as shown in the following
îš³gures.
44
Power Systems: Removing and replacing parts in the 9080-M9S system

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the IBM 9009-42G and is the answer not in the manual?

IBM 9009-42G Specifications

General IconGeneral
BrandIBM
Model9009-42G
CategoryPower Supply
LanguageEnglish

Related product manuals