Figure 610. Replacing the time-of day battery cover
4. Access the Advanced System Management Interface (ASMI).
Attention:
During this procedure: Do not reset the service processor, do not remove the service
processor card, and do not power off and power on the system.
5. In the navigation area, select Concurrent maintenance > TOD Battery.
6. In the ASMI TOD Battery panel, verify that the location code is selected, then press the Install Battery
button.
Preparing the 9080-M9S system for operation after removing and replacing
the time-of-day battery
Procedure
1. Ensure that you have the electrostatic discharge (ESD) wrist strap on and that the ESD clip is plugged
into a ground jack or connected to an unpainted metal surface. If not, do so now.
2. If you powered off the system to complete this repair, wait for the service processor comes up to the
Flexible Service Processor (FSP) standby state (the power-on LED on the control panel is flashing
slowly) then continue to the next step to validate all of the cables. If you did not power off the system,
skip the next step and continue to the step to validate only the UPIC cables.
696
Power Systems: Removing and replacing parts in the 9080-M9S system

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the IBM 9009-42G and is the answer not in the manual?

IBM 9009-42G Specifications

General IconGeneral
BrandIBM
Model9009-42G
CategoryPower Supply
LanguageEnglish

Related product manuals