12 Decommissioning, Storage and Transport
12.1 De-commissioning
De-commissioning is necessary, for example, under the following circumstances:
The machine is temporarily not needed
The machine will not be needed for a considerable time.
The machine is to be scrapped.
Precondition The machine is shut down.
Machine dry and cool.
1. Carry out the following de-commissioning procedures.
2. Place a notice on the instrument panel describing the de-commissioning procedures carried
out.
12.1.1 Temporary decommissioning
Decommissioning for about 4 months.
Material Plastic foil
Moisture-resistant adhesive tape
1. Disconnect the battery (the minus terminal first and then the plus terminal).
2. Close off the following openings with plastic foil and moisture-resistant adhesive tape.
Engine air inlet
Compressor air inlet
Exhaust
3. Hang the following notice on the instrument panel informing of the decommissioning measure‐
ments taken.
Attention!
1. The machine is temporarily decommissioned.
2. The following machine openings have been covered:
Engine air inlet
Compressor air inlet
Exhaust
3. Recommission according to service manual.
Date / signature
Tab. 66 "Temporarily decommissioned" information notice
Decommissioning of the compressor for several weeks during severe frost
1.
Danger of batteries freezing.
Discharged batteries are subject to frost damage and can freeze at 14 °F.
Store batteries in a frost-free place.
Store batteries preferably fully charged.
12 Decommissioning, Storage and Transport
12.1 De-commissioning
No.: 9_9446 01 USE