Manitowoc Published 08-06-19, Control # 237-09_v2 4-35
MLC165-1 OPERATOR MANUAL SETUP AND INSTALLATION
See Figure 4-30 for the remaining steps.
4. Attach lifting slings to the two lifting lugs (3) on the
counterweight box (2) as shown. Each box weighs
11,023 lb (5 000 kg).
Use either:
• Two legs of a chain lifting sling looped around the
lifting lugs and hooked to the master link.
• Two synthetic lifting slings vertically connected to
the lifting lugs and to the assist crane hook.
5. Lift the counterweight box (2) off the trailer and remove
the trailer.
6. Use the alignment lugs (4) on the tray to align the box.
7. Disconnect the lifting sling and repeat the process for
each box.
8. Use the alignment lugs (4) on each box to align the
adjacent box.
9. Stack the boxes as shown for either Series 1 or Series 2.