MLC165-1 OPERATOR MANUAL SETUP AND INSTALLATION
See Figure 4-51 continued.
8. Using the switch on the remote control, engage the inner
connecting pin (5, View F) on both sides of the rotating
bed.
9. Install the outer connecting pin (6, View A) on both sides
of the rotating bed.
10. Disconnect the shackles (1, View G) and the handling
chains (2) from the lifting links (3).
11. Using the switch on the remote control, fully retract the
counterweight-handling cylinders (4, View G).
12. Pin the shackles (1, View E) to the storage lugs (8).
13. Remove excess slack in the chains by wire tying them to
the tie-down lugs (9).
14. Travel the crane away from the counterweight tray (7).