PRE INSTALLATION
Milli-Q Synthesis/Synthesis A10 15
Chapter 3 PRE INSTALLATION
3-1 PRE INSTALLATION CHECKLIST
The installation of your Milli-Q will go much easier if certain pre installation requirements are met and followed.
The checklist below can be used to facilitate the pre installation of your Milli-Q system. You can refer back to this
checklist as you read the sections on Optional Equipment, Installation Requirements and Unpacking the Milli-Q Box.
Do you have a Q-Gard Purification Pack?
Do you have a Quantum Ultrapure Cartridge?
Do you have a Millipak?
Do you have a Milli-Q and all items in its Accessories Bag?
Do you have a source of electrical power close enough to the Milli-Q?
Is the electrical source earth grounded?
Are you feeding with a Reservoir? (if feeding from a pressurised pipe, see below)
Is the reservoir full of water?
Is the source of water filling the reservoir fully operational?
Does the reservoir have an 8 mm tubing connection on one of its valves?
Are you feeding the Milli-Q from a pressurised pipe (loop)?
Do you have a pressure regulator ready to connect between the pipe and the Milli-Q?
Is the water system feeding the pipe fully operational?
Does the pipe have a valve ending with a 1/2 inch NPTM connection? If not, do you have a fitting or
connection that will attach to the pipe and will end in a 1/2 inch NPTM connection?
Is there a way to shut off water from the pipe to the Milli-Q? If not, did you order a ball valve from
Millipore to install on the Feedwater Tubing?
Are you mounting the Milli-Q on a wall?
A wall mounting bracket may be needed in specific conditions
Will the wall support the weight of the Milli-Q (plus full reservoir, ...)?
Is the Milli-Q accessible at this height (viewing the LCD, using the keypad)?
Did you include space on the right side of the Milli-Q to remove and replace the Q-Gard?
Did you want a location so as to dispense water over a sink?
Is the Milli-Q located within 2.5 meters of a drain (for the UF Reject tubing)?
Is the Milli-Q located within 2.5 meters of a drain (for the Feedwater Pressure Relief Valve tubing)?
Are the room environmental conditions adequate (humidity, temperature)?
If you are going to connect a printer or computer to the Milli-Q later, did you leave room for this?
If you are using a footswitch accessory to control the Milli-Q, did you leave room for this?