A-8 Electrical Safety Inspection
ELECTRICAL SAFETY INSPECTION
5- Earth Leakage Test
Failure
Check any short-circuits of the Y capacitor on power unit. Replace a new one if any
portion defective.
Check any broken of the Power Unit. Replace a new one if any portion defective.
Inspect mains wiring for bad crimps, poor connections, or damage.
Test the wall outlet; verify it is grounded and is free of other wiring abnormalities.
Notify the user or owner to correct any deviations. As a work around, check the other
outlets to see if they could be used instead.
Change another probe to confirm if the fail is caused by console.
Inspect mains wiring for bad crimps, poor connections, or damage.
If the leakage current measurement tests fail on a new unit and if situation cannot be
corrected, submit a Safety Failure Report to document the system problem. Remove unit
from operation.
If all else fails, stop using and inform the Customer Service Engineer for analysis
and disposal.
LIMITS
IEC60601-1: 500 μA Normal Condition
1000 μA Single Fault Condition

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Mindray M9T and is the answer not in the manual?

Mindray M9T Specifications

General IconGeneral
BrandMindray
ModelM9T
CategoryMedical Equipment
LanguageEnglish

Related product manuals