6 Commissioning
6.1 Detector start-up
1. Connect the main power supply cable.
2. Set the main switch/circuit breaker to I.
3. For first start-up: set the language, unit, date and time (the user can modify these settings at a
later time).
4. Wait for the detector to enter “Stand-by” mode.
Start-up after an extended shutdown
If the detector has been stored or has not been used, start-up time is longer than if it is in regular use.
After a shutdown of the detector of more than 3 months, it is advisable to start up the detec-
tor 24 hours before its use.
6.2 Detector powering off
1. Set the switch/circuit breaker to O.
2. Wait for the control panel screen to turn off completely before working on the product, removing
the cover and/or moving it.
3. Disconnect the mains power cable.
Pump stop due to power failure
When there is a mains power failure, the detector shuts down: it switches on again automatically when
power is restored.