Installation
Preparing the analyzer for operation
1. Selecting language
Before the analyzer is turned on, the language setting has to be selected. The factory-
set language is English.
o Remove the paper tray and use a pen to set the switch to the desired language
position as indicated on the label.
q
If you decide to change the language after the unit is turned on, you have to restart the
analyzer to activate the new language.
2. Start-up
o Find the power switch on the back of the unit and make sure that it is in the OFF
(O) position.
o Plug the power cord into the power receptacle module on the back of the unit,
then plug the cord into a grounded electrical outlet (100–240 V, 50/60 Hz).
Figure 6-11
o Push the power switch to the ON (I) position. The unit will automatically begin to
operate.