SECTION IV
MAINTENANCE / SERVICE
4.31 Main Controller Board Removal /
Installation
A. Removal
DANGER
Table is very heavy. Use an assistant
to lay table onto its side. Failure to do
so could result in serious personal injury.
(1) Lay table onto its left side.
(2) Remove five screws (1, Figure 4-56) and battery
cover (2) from base weldment (3).
(26) Connect hose (3) to swivel fitting (4).
(27) Connect hose (1) to male connector (2).
(28) Install main cover (2, Figure 4-53) on base
weldment (3) and secure with six screws (1).
(29) Raise table to its upright position.
(30) Check adjustment by LOCKING floor locks.
Outrigger floor lock cylinders should not raise
table off of ground (with leg section installed).
Page 4-53Printed in U.S.A.
Figure 4-56. Control Box Removal / Installation
CA818600
5
1
2
3
6
7
8
9
11
10
4
4
© Schaerer Mayfield USA, Inc. 2004

Table of Contents