Operating Instructions FLOWSIC100
Gas Velocity Monitor
Assembly and Installation
88012513/03-2008 © SICK MAIHAK GmbH · Germany · All rights reserved 71
3.2.4 Mounting the Purge-air Unit Option
The steps below are only necessary if purged sender/receiver units are required.
The following points must be taken into account when selecting the mounting location:
The purge-air unit must be mounted at a location with clean air. The intake temperature
must match the values specified in the technical data (see Section 2.6). If necessary, lay
an intake hose at a location where the conditions are more favorable.
The mounting location must be easily accessible and fulfill all the applicable safety re-
quirements.
The purge-air unit must be mounted as far below the sender/receiver units as necessary,
so that the purge-air hoses can be installed falling towards the purge-air unit (avoiding
water collection).
Sufficient clearance must be provided for replacing the filter insert.
Sufficient clearance must also be provided for mounting and for raising the weatherproof
cover, if the purge-air unit is mounted outdoors (see Fig. 3.15).
Fig. 3.15: Mounting the purge-air unit
Installation work
Prepare the bracket as shown in Fig. 3.15.
Secure the purge-air unit with 4 bolts (M8).
Check whether the filter insert is installed in the filter housing; fit the insert if necessary.
> 160
550
> 140
550
Duct
Purge-air hose
Clearance
for
fitting of
weather-
proof
cover
Clearance for replacing filter insert
Purge-air hose
470
470
50
M 8
Alternative:
retaining bracket
50 x 5 steel pipe
DIN 2391