EasyManua.ls Logo

SICK DUSTHUNTER T - Page 268

SICK DUSTHUNTER T
552 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
FLOWSIC100 Operating Instructions
Gas Velocity Monitor
Assembly and Installation
76
©
SICK MAIHAK GmbH · Germany · All rights reserved
88012513/03-2008
Connecting/Commissioning the Optional Purge-air Unit
Compare the supply voltage and frequency with those specified on the rating plate of the
purge-air motor.
ATTENTION
Important
Do not connect the purge-air unit if the values do not match.
Connect the power supply cable to the terminals on the purge-air motor (see supplemen-
tary sheet on purge-air motor and cover of motor terminal box; see the connection arran-
gement shown in Fig. 3.20).
Connect a protective conductor to the terminal.
Set the motor circuit-breakers in accordance with the connection data of the fan (see
technical data of purge-air unit) to a value 10% greater than the rated current.
Check the functioning and running direction of the fan (flow direction of the purge-air unit
must match the arrows at the inlet and outlet openings on the fan). If the direction of run-
ning on 3-phase motors is incorrect, swap power connections L1 and L2.
Connect the (optional) pressure monitor for monitoring the purge-air supply.
Important
ATTENTION
Use a fail-safe power supply (emergency power supply, bar with redundant supply)
The purge-air unit must be fused separately from the other system components. The fuse
type must match the rated current (see technical details of purge-air unit). Fuse each
phase separately. Provide circuit-breakers to protect against a phase failure on one side.
If you are in doubt, or if you are using a special motor version, the operating instructions sup-
plied with the motor should take priority over any other information.
Fig. 3.20: Electrical connections for the purge-air unit
Power supply
4 x 1.5 mm
2
L1 L1
U1 U1
U1
U1
V1 V1
V1
V1
W1 W1
W1
W1
PE PE
W2 W2
W2
W2
V2 V2
V2
V2
U2 U2
U2
U2
L2 L2
+
24 V
L3 L3
_
PE PE
Low-pressure sensor
delta connection star connection
Fan motor in
Installed by
customer
Motor
circuit-
breaker

Table of Contents

Related product manuals