S7-300 Programmable Controller Hardware and Installation
A5E00105492-01
8-1
8Commissioning
8
8.1 In this Chapter
In this chapter
contains notes on commissioning which you should take into account in order to
avoid personal injury or damage to machines.
Note
Since your commissioning phase is determined primarily by your application, we
can only offer you general information, without claiming completeness of this topic.
Always note ...
the information on commissioning in the description of your system elements and
devices.
8.2 Commissioning procedure
Software requirements
To utilize the full functional scope of the CPUs, you require
• STEP 7 as of V 5.1 + SP 2 for CPUs 31xC
• STEP 7 as of V 5.x for all other CPUs
Prerequisites for commissioning
• S7-300 is installed
• S7-300 is wired
• With networked S7-300:
– MPI/PROFIBUS addresses are configured
– The segments are terminated with active terminating resistors

Table of Contents

Other manuals for Siemens 6ES7 305-1BA80-0AA0

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens 6ES7 305-1BA80-0AA0 and is the answer not in the manual?

Siemens 6ES7 305-1BA80-0AA0 Specifications

General IconGeneral
BrandSiemens
Model6ES7 305-1BA80-0AA0
CategoryController
LanguageEnglish

Related product manuals