System integration   
9.1 ASM 452 
  MOBY D 
238  System Manual, 01/2010, J31069-D0147-A6-7618 
9.1.6  Cable 
9.1.6.1 PROFIBUS DP cable with 24 V supply 
The ASM 452 can also be operated with the "green" PROFIBUS DP cable. It is important to 
ensure that a 24 V cable is connected from X12 to X13. The 24 V cable can be connected to 
pins 5 and 6 in plug X12. 
 
;
;
;
;
;
;
 
Figure 9-7  PROFIBUS DP cable with 24 V supply 
9.1.6.2 Example of stripped lengths 
The following diagram shows an example of stripped lengths. The lengths apply to all cables 
which can be connected to the connector plugs. You must twist any shield braid present, 
plug into a core end sleeve and cut off any excess. 
 
7ZLVWHGDQG
WUXQFDWHG
VKLHOGEUDLGLQJ
 
Figure 9-8  Length of stripped insulation for PROFIBUS DP cables