Commissioning
12.2 Check before powering on for the first time
S7-1500R/H redundant system
System Manual, 01/2024, A5E41814787-AF
361
12.2 Check before powering on for the first time
Before the first power-on, check the installation and the wiring of the S7-1500R/H redundant
system.
Questions for checking
The following questions provide instructions for checking your system in the form of a
checklist.
Rack
Are the rails firmly mounted to the wall, in the frame, or in the cabinet?
Are the cable ducts correctly installed?
Have the minimum clearances been observed?
Grounding concept
Are the rails connected to the protective conductors?
If applicable, are all further protective conductor connection points on the S7-1500R/H
redundant system connected to the protective conductor? Has the protective conductor
been tested?
Are the required equipotential bonding cables connected with low impedance to the
relevant sections of the plant?
Module installation and wiring
Are all the modules inserted/installed in accordance with the installation schedule and
STEP 7 configuration, and screwed firmly to the rails?
Have all synchronization modules been installed and locked in the S7-1500H redundant
system? You should hear the modules click into place in the module slots.
Are all redundancy connection connectors in the S7-1500H redundant system correctly
connected to the LC sockets? You should hear the connectors click into place in the LC
sockets.
Are the redundancy connections (PROFINET cable) between the CPUs in the S7-1500R
redundant system connected to the correct ports of PROFINET interface X1? The ports
used must correspond to the configuration in STEP 7.
Are the PROFINET devices in the S7-1500R/H redundant system connected?
System power/load current supply
Are all system power/load current supplies switched off?
Is the power cable connector correctly wired?
Has the connection to line voltage been established?

Table of Contents

Other manuals for Siemens SIMATIC S7-1500T

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens SIMATIC S7-1500T and is the answer not in the manual?

Siemens SIMATIC S7-1500T Specifications

General IconGeneral
BrandSiemens
ModelSIMATIC S7-1500T
CategoryController
LanguageEnglish

Related product manuals