5. Click on "Load" to confirm the load operation.
Dialog "Load preview" opens.
Figure 6-10 Load preview IPC
Note
Consistency check
Before the loading, the consistency of the download is checked. This means that a check is
performed as to whether the parameterized hardware of the TIA Portal project matches the
hardware that has actually been installed.
Note
Adapt the IP address?
If the IP address of your PG/PC is located in a different subnet than the IPC, a dialog box is
displayed indicating whether the IP address in the PG/PC should be adapted.
6. Check the settings in dialog "Load preview". To confirm the entry, click on "Load".
Result
The software configuration is loaded to the IPC. The "Results of the loading action" dialog
opens and displays the status of the loading action.
Commissioning and configuring
6.4 Load the configuration into the control system
Safety Integrated (with SINAMICS S120)
Commissioning Manual, 02/2020, A5E46305916B AB 247