36
– The "Conrmation" menu is then displayed.
6. Check the data in the "Conrmation" menu.
7. To complete initial start-up, press .
– The main menu will then be displayed (see Section 7.4).
– In the case of commissioning in Italy, after initial start-up the auto test must be
carried out (see Section 6.3).
6�2�3 Country-specic menus
Depending on the country setting, additional menus will be displayed during initial
start-up.
Country: Denmark
Menu Setting Description
Plant system rating > 13.8 kVA – 30 kVA* The plant system rating is higher than 13.8
kVA and does not exceed 30 kVA.
> 30 kVA The plant system rating is higher than 30
kVA. External grid monitoring will be used.
CosPhi(Pac) - QMCPP Inactive
The "cosφ(Pac)" function is deactivated
(cosφ=1).
On
The "cosφ(Pac)" function is activated.
* only available with the SM30HT4
Country: Germany
Menu Setting Description
Grid connection Medium voltage The inverter is connected to the medi-
um-voltage mains.
Low voltage The inverter is connected to the low-voltage
mains.
System power* > 13.8 kVA – 30 kVA** The plant system rating is higher than 13.8
kVA and does not exceed 30 kVA.
> 30 kVA The plant system rating is higher than 30
kVA. External grid monitoring will be used.
CosPhi(Pac) - QMCPP* Inactive
The "cosφ(Pac)" function is deactivated
(cosφ=1).
On
The "cosφ(Pac)" function is activated.
* only available with "Low-voltage" grid connection
** only available with the SM30HT4