10 Decommissioning
10�1 Instructions for inverter replacement
When replacing the inverter, note the following:
Before replacing the inverter, write down the total yield. The procedure for viewing
the total yield is described in Section 7.5.4.
102 Dismounting the inverter
The inverter may only be dismounted by qualied electricians.
DANGER!
Fatal electric shock hazard!
Components within the inverter are charged with a high voltage. After the
inverter has been disconnected, high residual voltages remain in the inverter
for approx. 5 minutes.
Before starting to dismount the inverter, the inverter must be fully discon-
nected in accordance with the procedure described in this chapter.
WARNING!
Risk of injury from electric arc!
Dangerous electric arcs could occur when removing live DC input conductors.
Switch off the DC disconnector before removing the DC input
conductors.
Procedure
1. Disconnect the AC power supply to the inverter (switch off the external AC circuit
breaker).
The "No grid" status message is shown on the inverter.
2. Switch off the DC disconnector at the inverter.
O
Figure 44 Switching off the DC disconnector
3. Use a size 2 screwdriver to remove the locking clips on the DC plugs.