Getting Ready to Pave
Topcon Paver System Five Operator’s Manual
5-14
Once the slope sensor is calibrated and you are ready to begin
paving, you may find the existing surface does not have the same
slope as the finish design.
In order to produce a smooth transition, begin paving at the existing
slope and slowly turn the grade adjustment knob to change the cross
slope to the correct percentage.
Figure 5-16. Producing a Smooth Slope Transition
If a smooth transition is not required, then dial in the desired slope
and begin paving.