Configuration and Programming
P/N 06-237041-001 3-31 February 2011
36 Alarm Verify. Change the Smoke-Detectors’ Alarm-Verification-Delay Period. Purpose: To
change the period of time that the FenwalNET 8000-ML control unit will wait for a second,
confirming signal from a smoke detector (or any other alarm-initiating device) that an alarm
condition is valid and actually exists. The alarm verification period is programmable from 30 to
180 seconds in one-second increments, or 0 (zero).
37 PAS. Change the Smoke-Detectors’ Positive-Alarm Sequence Investigation Period. Purpose:
To change the period of time that the FenwalNET 8000-ML control unit will wait for the occupants
to investigate a smoke-detector’s positive-alarm-sequence report before it executes the smoke-
detector's programmed alarm actions. The operator must reset the control unit before this time
period expires or the programmed alarm actions will occur.
38 Nightly Test Time. Purpose: To set the time, once per night, when the panel performs a SLC
device test.