en Shut-down
78 WILO SE 2019-07
Switching cycles: Pump 1
Switching cycles: Pump 2
Switching cycles: Pump 3
Serial number
Display switches between the 1st and 2nd four digits.
Switchgear type
Software version
Set value for the motor current monitoring: Pump 1
Max. rated current in A
(“Control EC-Booster” only)
Set value for the motor current monitoring: Pump 2
Max. rated current in A
(“Control EC-Booster” only)
Set value for the motor current monitoring: Pump 3
Max. rated current in A
(“Control EC-Booster” only)
Actual current for pump 1 in A
Display alternates between L1, L2 and L3
Press and hold the operating button. The pump starts after 2s of
pumping operation until the operating button is released.
(“Control EC-Booster” only)
Actual current for pump 2 in A
Display alternates between L1, L2 and L3
Press and hold the operating button. The pump starts after 2s of
pumping operation until the operating button is released.
(“Control EC-Booster” only)
Actual current for pump 3 in A
Display alternates between L1, L2 and L3
Press and hold the operating button. The pump starts after 2s of
pumping operation until the operating button is released.
(“Control EC-Booster” only)
9 Shut-down
9.1 Personnel qualifications
Electrical work: A qualified electrician must carry out the electrical work.
Installation/dismantling: The technician must be trained in the use of the necessary
tools and fixation materials for the relevant construction site.
9.2 Operator responsibilities
Observe locally applicable accident prevention and safety regulations of trade associ-
ations.
Make sure that the personnel has had the corresponding training for the specified work.
Train the personnel on how the system operates.
When working in enclosed spaces, a second person must be present for safety reasons.
Ensure enclosed spaces have sufficient ventilation.
Take immediate countermeasures if there is a build-up of toxic or suffocating gases!
9.3 Shut-down
To decommission the pumps, switch off the pumps and switchgear at the main switch.
The settings are stored in non-volatile memory in the switchgear and are not deleted.
This ensures that the switchgear is always ready for operation. Adhere to the following
points during the standstill period:
Ambient temperature: 0 … 40°C
Max. humidity: 90%, non-condensing