PN 305200901, Rev YT
Pre-Installation Requirements
Personnel Technical Level Required for Installation
The operations in this section should be performed only by qualied
service personnel experienced in electrical safety techniques. Never
service the analyzer unless power has been removed from the analyz-
er, and the analyzer has been allowed to cool for at least 90 minutes.
Also, always use gloves when working on the analyzer.
Storage Prior to Installation
If the analyzer is stored for any period of time prior to installation, store the
equipment in an environment where it is not subject to dripping or splashing
liquids, corrosive gases, high humidity, or excessive heat or cold. Recommend-
ed storage conditions include:
Temperature: 0 °C to 50 °C (32 °F to 122 °F)
Relative Humidity: <90 %, non-condensing
Failure to comply with these storage conditions will void your warranty.
Analyzer Site Preparation
Observe the following guidelines when selecting an analyzer installation loca-
tion:
• Space Requirements
The bench top model requires a bench area of approximately
25cmx30cm plus clearance for analyzer connections and external com-
ponents. Refer to Figures 2-1 and 2-2.
• Select a readily accessible location for the analyzer to allow for routine
maintenance. Comfort levels for maintenance personnel should be consid-
ered in placement of the analyzer.
• The installation location should be free from excessive vibration and
the ambient temperature is required to be within the limits listed in the
specications (refer to Chapter 5). If the ambient temperature is outside
the specied limits or the vibration is excessive, contact your AMETEK
representative to discuss solutions and special options to address ambi-
ent temperatures.
2-2 | 3050-OLV Moisture Analyzer