16. Preventive Maintenance
16.2 RECOMMENDED MAINTENANCE
16.2.1 Routine
Any time other work is being done on the Instrument, the
following should also be done.
Check and repair, replace, adjust or tighten as required:
Hydraulic leaks
Worn parts
Loose parts and connections
Discolored wires, terminals, relay contacts, and tubing
Inspect valves, switches, motors, relays, circuit breakers,
etc., for signs of water leaking onto the component.
Replace wetted components.
Clean or replace concentrate line filters
Inspect concentrate fitting O-rings and replace as needed
Inspect dialyzer connector O-rings and replace as needed
Check fan filter and clean or replace as needed
16.2.2 Annual
Replace internal arterial and venous level adjust/pressure
monitoring system transducer protectors.
Replace UF flow meter diaphragm (J040700).
Clean Instrument interior (including dust removal and fan
filter).
Clean blood leak detector lenses.
(Every two years) Replace flow equalizer diaphragms
(J0171700).
Perform all functional verifications (see Section 19), and
calibrate as necessary.
16.2.3 As Required by Local Code
Check:
Line cord ground continuity
Leakage current
16.2.4 Before Prolonged Storage
Disinfect and drain the fluid path.
Refer to Section 9, Disinfection, for fluid path disinfections, and
Section 28, Installation, for instructions on long-term storage.