16. Preventive Maintenance
Arena Hemodialysis System
MAINTENANCE LOG
Clinic: __________________________________ Completed by: ______________________________
S/N________________ Date ______________ Instrument Hours___________ Next PM ________
Maintenance
Parts Serviced: Replaced Cleaned Other parts used:
Blood leak detector
Overflow Drain & Drain Line
Fan Filter
Dialyzer connector O-rings
Concentrate fitting O-rings
Postdialyzer Filter
Predialyzer Filter
Concentrate line filters
Flow equalizer diaphragms
UF flow meter diaphragm
Internal A/V transducer
protectors
Calibration
Use Calibration Worksheet at the end of Section 18.
Functional Verification
Use Functional Verification Data Sheet at the end of Section 19.
157-1278-923 Rev A 16-17
February 2004