4.3.1 Final pre-departure checklist
− Check rudder operation by putting the rudder hard over to port and
starboard, and then back to the center.
− Check trim tabs operation. Operate both tabs.
When not in use, trim tabs should be kept in the UP position.
− Check navigation lights and horn operation.
− Check the efficiency of the anchor winch and chain stopper.
− Check VHF radiotelephone operation.
− Check documents and nautical charts.
− Check proper closing of portlights and hatches and that all loose items
are secured on main deck and belowdeck.
− Check operation of bilge pumps and related indicators.
− Make sure that the engineroom ventilation system is operating.
− Check that no flammable or other hazardous materials are stowed in
the engineroom.
− Check that seawater intake valves for engine and generator cooling
and for air-conditioning system are open.
− Check that the engines and generator fuel systems’ valves are open.
− Switch on engine and user batteries.
− Switch on all 24 V circuits from the switch panel board. Check the
proper operation of each system and then switch off the systems not
to be used.
− Check the battery charge level (Volts) on the switch panel board.
Recharge the battery if indicated.
− Start the generator if you are to use it. Allow the generator to warm up
before adding electrical loads to it from the switch panel board.
− Disconnect the shore connections for fresh water and electric power,
cables and telephone.
− Check the fixed firefighting systems and the portable (hand-held) fire
extinguishers.
− Check fuel system for no leaks or fumes.