Example "B" :
Dimension 5,3 mm
Dimension - 3,2 mm
Difference = Plate clearance 2,1 mm
NOTE :
In case of deviations from the required plate
clearance, correct by means of corresponding
compensating plates.
The pre-assembly of the remaining clutches (K3,
KV/K1 and KR/K2) has to be carried out accordingly.
3.2.3.3 Pre-assemble and install spur gear K4
ATTENTION :
According to the Transmission Version, resp.
operating conditions, different spur gear bearings
are possible, see corresponding Spare Parts List as
well as Figures 143 and 144 !
Spur Rear K4, Version "A" (Figure 143)
1 = Thrust plate 5 = Spur gear
2 = Thrust washer 6 = Bearing inner race
3 = Collar shim 7 = Shim
4 = Roller cage (2x)
Spur gear K4, Version (Figure 144)
1 = Thrust plate
2 = Thrust washer
3 = Spur gear
U = Needle cage
5 = Thrust washer
6 = Thrust washer
7 = Compensating plate (optional)
Install components 2 ... 6 (Figure 143), resp. 2 ... 4
(Figure 144), replace thrust plate (1) and introduce
spur gear until all inner plates are received.
NOTE :
Make thrust plate (2) adhere with grease !